INC-2026-0139

HIGHClosed

Reported by Robert Kim — Electrician

19 February 2026 at 06:45 pmPower StationHazard ReportElectrical (Isolation/LOTO)Night Shift

Incident Description

Switchboard panel cover found unsecured on Unit 3. Arc flash hazard present. Previous maintenance work order had not been closed out properly.

Immediate Actions Taken

  • 1Panel secured immediately
  • 2Work order audit initiated
  • 3Exclusion zone maintained until inspection

Likelihood x Consequence Matrix

InsignificantMinorModerateMajorCatastrophic
Almost Certain
Likely
Possible
Unlikely
Rare

Likelihood

3 / 5 — Possible

Consequence

4 / 5 — Major

Risk Score

12/25

Failed / Breached Controls

Exclusion Zone Signage

Signage not visible in dusty conditions

HIGH
Effectiveness
15%

Spotter Positioning

Spotter not in designated position

HIGH
Effectiveness
0%

Controls That Held

Vehicle Speed Limits

LV was within speed limits when entering zone

Effectiveness
80%

Operator Awareness

Haul truck operator noticed LV and stopped

Effectiveness
85%

Incident Reporting

Reported immediately via radio

Effectiveness
95%

Priority Questions

  • What were the direct and contributing causes of this incident?
  • Were all relevant procedures followed by personnel involved?
  • Was there adequate supervision at the time of the incident?

Follow-Up Questions

  • Were there any similar incidents in the past that could have predicted this?
  • Were all personnel adequately trained for the task being performed?
  • Were environmental conditions a contributing factor?

Systemic Questions

  • Does this incident indicate a gap in the current risk management framework?
  • Are there systemic issues with procedure adherence in this area?
  • Would additional engineering controls reduce the likelihood of recurrence?
06:30 pm

Pre-start meeting completed

06:45 pm

Incident occurred

06:50 pm

Incident reported to supervisor

06:55 pm

Area secured and barricaded

07:05 pm

HSE team notified and on-scene

07:30 pm

Initial investigation commenced

07:45 pm

Report filed in SafetyScribe AI

Incident Details

Date & Time

19 February 2026 at 06:45 pm

Location

Power Station

Type & Category

Hazard Report

Electrical (Isolation/LOTO)

Severity
High
Status
Closed
Shift

Night Shift

Reported By

Robert Kim — Electrician

  • Night Shift Electrician — Robert Kim
Night shiftIndoor
Switchboard PanelUnit 3 Generator